
MAINE
8)
Can contractors be debarred?
A.) The information provided is vague when it comes to the issue
of debarment because of a prevailing wage violation. However,
B.) If a contractor is disqualified for any of
the reasons stated in subsection 1, 2, 4, 5, 6 or 7, the director
may disallow the contractor from bidding on any similar public
improvements for a period not to exceed one year. (1747)
* The number 3 is not included in the above reasons
for disqualification.
C.) The Director of General Services, after consultation
with the appropriate department head or superintendent of schools,
may refuse to release plans and specifications to a contractor
for the purpose of bidding on a project: (1747)
1.) Untimely completion. If, in the opinion of
the director, there is evidence the contractor has not completed
in a timely manner a prior construction project or projects
and the resulting non-completion clearly reflects disregard
for the completion date and has created a hardship for the owner;(1747)
2.) Incomplete work. If, in the opinion of the director, there
is evidence the contractor has a history of inability to complete
similar work; (1747)
3.) Insufficient resources. If, in the opinion of the director,
there is evidence the contractor does not have sufficient resources
to successfully complete the work. The director may require
additional information about the contractor's resources, including
identification of major claims or litigation pending and whether
the contractor has sought protection under the bankruptcy laws
in the past 5 years. That information is confidential and not
subject to disclosure under Title 1, chapter 13, subchapter
1. In evaluating the resources of a contractor, the director
may consider the contractor's prior experience, including any
significant disparity between the size and type of prior projects
and the project or projects under consideration; (1747)
4.) Misconduct. If the contractor has been convicted of collusion
or fraud or any other civil or criminal violation relating to
construction projects;(1747)
5.) Safety record. If, in the opinion of the director, there
is evidence of a history of inadequate safety performance and
lack of formal safety procedures;(1747)
6.) Material misrepresentation. If, in the opinion of the director,
there is evidence of a material misrepresentation on the contractor's
pre-bid qualification statement; or (1747)
7.) Termination, suspension, defaults. If, in the opinion of
the director, there is evidence that the contractor through
its own fault has been terminated, has been suspended for cause,
has been debarred from bidding, has agreed to refrain from bidding
as part of a settlement or has defaulted on a contract or had
a contract completed by another party. (1747)
* This information is taken from Title 5, Section
1747.